Set Up for Schedule

M ColonMember for 25 years 8 months
Created
4
2
0
In order to have an accurate schedule that will serve the needs of the project team, that is management and constructability, there are 3 key elements that have to be brought up from the inception of the project:

1. Contract Requirements Specifications and Plans

2. From the first requirement the "estimator" should develop a budget that should consider all aspects of the project including time, material, equipment, and overhead and profit

3. After the first two requirements are satisfied, then the scheduler may start developing a plan (usually this plan is thought out alond with a superintendent or a constructability expert).

From the estimate all key equipment and material should be identified, therefore productivity rates can be found using Means. Make a note that phasing on the project will affect sequency and poductivity should be adjusted to satisfy this fact.

Construction sequency should follow the plans and must take into consideration existing conditions of the site. The sequence longest path should be worked out so that essential components on the schedule fall in the critical path and determine the float.

4 replies

Oldest first
  1. 0
    Ed van der Tak ·
    Is this a question?

    As a respons to your information please note that historical project info (similar projects within the organisation or branch) are essential to get a uniform way of scheduling projects. Budget breakdowns are costgroup based and not neccesarily useful for making good schedules.

    Regards,

  2. 0
    Ernesto Puyana ·
    That’s exactly what I meant to address in my post on CBS vs WBS.
    Cost groups are not an appropiate guide to organize a schedule on their own. They ignore space and time. I usually apply them at a third level in the breakdown, after Area and Phase divisions.
  3. 0
    Ali Hamouda ·
    Hi,

    About setting up a schedule, I would like to have more detailed discussion about this topic.

    For example:on what bases we divide the project on to Zones and phases?

    one of the new projects that I am working on now,

    has this problem: external walls is precast,this force me to divide the building to Inner zone and outer zone,because the precast will be instatalled after the building skeltone been done.and there is block work to be done after the precast,in this case the problem of finishes will arise, that is why dividing the building to Inner and Outer zone is a must.

    In advance thanks for your sharings.

    Ali
    -----------------------
  4. 0
    William Stakelin ·

    Precast

    I see no difference in a building with precast then any other building. Of course you have to set your precast before setting the metal studs on the exterior walls. compared to a structure with, lets say, Brick, where you have to set your exterior wall studs and dense glass first. Other then changing when (in time) that the metal studs for the exterior walls are set into place I see no problems.

    Just a thought.
    William

Log in or join to reply