Using Planning Planet Rates???
In the Open Standard
Darrell ODeaMember for 24 years 7 months
- Created
- 0
- 3
0
Has anyone out there used the Plannin Planet rates on a real Tender / Contract / Job ?
If so did or how did you qualify them ?
Would like to know, as I have had a bit of debate in the past about actual functional use of said rates.
And personally would not have much confidence unless qualification was attached.
e.g. If I said I could do Six Piles a day, what would that mean 2 U?
With a Rig ?
With a Tripod ?
How many Rigs / Tripods etc ?
What diamater ? Deptht ?
With / without tubes / cages etc. etc etc.???
Know what I mean, or do I need to qualify further?
Comments please.
D.
If so did or how did you qualify them ?
Would like to know, as I have had a bit of debate in the past about actual functional use of said rates.
And personally would not have much confidence unless qualification was attached.
e.g. If I said I could do Six Piles a day, what would that mean 2 U?
With a Rig ?
With a Tripod ?
How many Rigs / Tripods etc ?
What diamater ? Deptht ?
With / without tubes / cages etc. etc etc.???
Know what I mean, or do I need to qualify further?
Comments please.
D.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?