Skip to content

Project performance metrices for a portfolio of projects

Evgeny Z.Member for 18 years 9 months
Created
7
4
0
Dear all,
 
I am just wondering whether there are any accepted metrics for tracking a schedule-related performance of a group of projects, rather than an individual project.
 
E.g. for example for an individual project there is a Schedule Performance Index. But what about a group of projects? Is there anything like that?
 
We have to assume that if we have a portfolio of active projects, then at each individual given moment of time all projects will be at a different period of their life. Some of them will be just starting, others will be about to be finished.

7 replies

Oldest first
  1. 0
    Bian Mutang Tagal ·

    Hi Evgeny,It's true that any

    Hi Evgeny,

    It's true that any given moment of time each project will be at a different phase. However, assuming each project in a group of projects are assigned their own baseline then a set of PV (Planned Value) and EV (Earned Value) values corresponding to each project could also be calculated. At the WBS level that contains all these projects, the PV and EV can be aggregated based on cost, and thus the overall SPI calculated.

    So PV =  ΣBCWS

    where ΣBCWS = Budgeted Cost of Work Scheduled for all projects as of the data date (which should be the same for all projects)

    and EV =  ΣBCWP

    where ΣBCWP = Budgeted Cost of Work Performed for all projects as of the data date

  2. 0
    Zoltan Palffy ·

    you can take all of you

    you can take all of you project add them together and then tivided by the total number of projects  

    or

    you can take each individual project and give them a weight. Then determine your overall performance based on the weighted average. 

  3. 0
    Zoltan Palffy ·

    you can take all of you

    you can take all of you project add them together and then tivided by the total number of projects  

    or 

    you can take each individual project and give them a weight. Then determine your overall performance based on the weighted average. 

  4. 0
    Rodel Marasigan ·

    It should be the same matrics

    It should be the same matrics of whatever standard that your company is using. It will just elevated to a higher level.

  5. 0
    Vladimir Liberzon ·

    Evgeny,project portfolio has

    Evgeny,

    project portfolio has its own success criteria like NPV, IRR or something else.

    Estimating portfolio performance look what happens with the portfolio success criteria forecasts.

  6. 0
    Vladimir Liberzon ·

    Evgeny,project portfolio has

    Evgeny,

    project portfolio has its own success criteria like NPV, IRR or something else.

    Estimating portfolio performance look what happens with the portfolio success criteria forecasts.

  7. 0
    Lv Grace ·

    Hi Evgeny, good question, I

    Hi Evgeny, good question, I have the same question. 

    the all the subproject in different EPC phase, it is best to use the project cost as the project weightage for performance index.

    but for me, I need measure the project in the same phase, and each subproject executes team is from different region, or the same region but different team, how to measure their performance? if you want to do the portfolio, the projects coding is a challenge. I am wanting the Mega/Complex project coding structure.

    all, if you have any solution ,pls. give me a suggestion.

     

    Best Regards,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?