Plan Value
In the Open Standard
Noor ArieMember for 20 years 7 months
- Created
- 3
- 3
0
Hi all’
Sorry for questioning this, since i am new here and i don’t know wether this had been questioned before.
I have been using custom data item to create the percentage of Plan calculated from Plan Value. The figure will be used and modified weekly to support information to the Project Team which activities are behind and what is our next week plan %.
Since we have been behind from the early start of the project, the PMT decides to use the average % for plan in the S-curve. The question is how can i make the plan value to show the average instead of Early so i can measure each activity to the average percentage.
Thanx,
Sorry for questioning this, since i am new here and i don’t know wether this had been questioned before.
I have been using custom data item to create the percentage of Plan calculated from Plan Value. The figure will be used and modified weekly to support information to the Project Team which activities are behind and what is our next week plan %.
Since we have been behind from the early start of the project, the PMT decides to use the average % for plan in the S-curve. The question is how can i make the plan value to show the average instead of Early so i can measure each activity to the average percentage.
Thanx,
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?