The Procedures for Planning and Scheduling

Arnold PamplonaMember for 20 years 4 months
Created
103
16
0

Could someone explain and describe briefly the following:

1) Procedure to set up plan for a typical project:

2) Construction project reporting and control procedure for a project:

3) Procedure for the Procurement and Engineering plan for a typical project:
 

103 replies

Oldest first
  1. 0
    Benito Nepomuceno ·
    Peter,

    Thanks a lot for your immediate response. It is really big help for all planners!

    Best Regards,
    Benito
  2. 0
    Rajeev Kumar ·
    Peter,

    I would grateful if you could pass me a copy as well at tlrajeev@gmail.com

    Many thanks in advance.

    Rajeev
  3. 0
    Susan Young ·
    Peter,

    Could you please mark me a copy too at sussaa2001@hotmail.com

    Thanks

    Susan
  4. 0
    James Barnes ·
    Seems your Guide is popular Peter,

    if you could email me a copy to ajamesbarnes -at- barnes-diamant.com I’d be interested to take a look.
  5. 0
    Ashraf Alawady ·
    Dear can i have a copy at ashraf_abdlmonem@yahoo.com
    Regards
  6. 0
    R. Catalan ·
    Hi Peter,

    Could you please drop me a copy of your procedure as well at rrcatalan@hotmail.com
  7. 0
    Nar Thap ·
    Hi Peter,
    could you drop teh manual at narnor2002@yahoo.com? your help is much appreciated.
    Thanks
  8. 0
    Ruel Bacani ·
    Hi Peter,

    me too rrbacani23@yahoo.com
  9. 0
    Peter Holroyd ·
    James,
    still get knocked back on your yahoo address.
    Please confirm, RGds
  10. 0
    Luca Basile ·
    Hi Peter
    can please send to me too. (at "engbasile@yahoo.com")

    Thanks
    Luca

  11. 0
    Özgür Kılıç ·
    Hi Peter;

    Could you please send me a copy also.

    unsolvedproblem@yahoo.com

    Thank u very much

    Free.
  12. 0
    Özgür Kılıç ·
    Peter;

    I just took your email.
    Thank u for your really fast mailing.

    Free
  13. 0
    Adedeji Adelaja ·
    Hi Peter,

    Could you or anyone who has a copy of the SOP please send me a copy also.

    demajek@yahoo.com

    Thanks
  14. 0
    Ryan Medina ·
    Mr.Peter ,

    Can you please send me the SOP at kamelyon77@yahoo.com.Thanks
  15. 0
    Nar Thap ·
    Hi Peter ,
    Thanks for your docs.
    Really helpful.
    Cheers
  16. 0
    Leonard Mon ·
    Hi Peter & Nar,

    Good day..

    May I request you to send me also your docs as I believed this will be of help to me as well. My email addie is leonardcasero@yahoo.com

    Thanks in advance.
    Leonard
  17. 0
    Prabhu Chakravarthy Rathinavadivel ·
    Hi Peter,

    Could you or anyone who has a copy of the SOP please send me a copy also.

    prabhu.chakravarthy@alfanar.com

    Thanks and Regards
  18. 0
    Johny Kesserwany ·
    Can I have please a copy too!

    jkesser@hotmail.com

    Thank you,

    JK
  19. 0
    Prabhu Chakravarthy Rathinavadivel ·
    Hi Peter ,
    Thank you for the Documents ,

    The Document is really good and worth reading ,

    Thanks and Regards

    R. Prabhu Chakravarthy
  20. 0
    Amreshwar Shukla ·
    Can I have please a copy too!

    SHUKLA@MYREALBOX.COM

    Thank you,

  21. 0
    Ashraf Alawady ·
    Can I have please a copy on ashraf_abdlmonem@yahoo.com
  22. 0
    A D ·
    There’s a small envelope ICON next to the PP members name.

    Just click on it and you can send Private Message (PM) to get a copy of paper rather than sending a post every time.

    This will definitely save time of PP Members who always peep into these posts.

    :-)
  23. 0
    Reeja Raj ·
    Can I have please a copy on


    reejabraj@yahoo.com
  24. 0
    khan Rafiq ·
    I am a new memeber, i read this n feel i would be happy if u could pls send me a copy at rafiqkhan05@gmail.com
    Regards,
    khan
  25. 0
    Adelfa Sapinoso ·
    hello mr. peter!

    would GREATLY appreciate having a copy too! acanam@gmail.com

    advanced thank you!
  26. 0
    Salar Al Zubaidi ·
    Gents,

    I have received lots of requests from colleagues around the world about the aforementioned Docs but I think I was from the firsts who asked for it till now I didn’t! Can anyone help me to receive it?

    Cheers
  27. 0
    Ranganathan Rangaswamy ·
    Can I also have a copy,since i am new to planning it will be of much helpful. Your help is highly appreciated

    My email id is rrranganathan@yahoo.com

    tks n rgs


    Ranga Ran
  28. 0
    Gerry Politan ·
    Hi Peter,

    if u could spare me a copy too i would very much appreciate it. thanks...

    pls send to glpolitan@yahoo.com

    gerry
  29. 0
    Ricardo, Jr. Chua ·
    Hi Peter,

    Could send me a copy as well? My e-mail is ricardo.chua@fluor.com. Thanks & regards,

    Rick
  30. 0
    Shaiju Thomas ·
    Hi peter,

    Please send me a copy as well. my id is shaijuksa@yahoo.com

    Thanks & Regards
  31. 0
    Bambang Wicaksono ·
    Gentlemen,

    Could you please kindly pass me a copy as well.

    my email/id is bwicaksono2000@yahoo.com

    Regards,

    Bambang
  32. 0
    Peter Holroyd ·
    Hi, planners
    I have sent out many copies.
    If I have missed anybody please drop email address to the private message inbox
    Peter
  33. 0
    Anu Tor ·
    Hi, Peter

    I am a new planner and want to learn the planner system. Could you send me the procedure for planning and schedule at this e-mail : anuchard_397@yahoo.com?

    Thanks,
  34. 0
    Salahuddin Ahmed ·
    Hi Peter,

    Could you please send me a copy, my email is salah.ahmed80@yahoo.ca

    Thanks in advance
    Salah
  35. 0
    Gopala Iyer Sriraman ·
    Peter,


    Could you forward me the procedures to my e mail address .

    srgopala@gmail.com

    Cheers,
  36. 0
    Shiv Rao ·
    Also to me please

    jayshiv26@hotmail.com


    thanks

    Shiv Rao
  37. 0
    Prabhu Chakravarthy Rathinavadivel ·
    Hi ,
    I Have sent you the Copy of the Planning Procedures ,
    to
    ’mbedjaoui@gmail.com’’anuchard_397@yahoo.com’; ’srgopala@gmail.com’; ’bwicaksono2000@yahoo.com’; ’haijuksa@yahoo.com’; ’glpolitan@yahoo.com’; ’rrranganathan@yahoo.com’

    Have a Nice Day ,


    Enjoy
  38. 0
    Abdelrahman Alsayed ·
    Also to me please

    abdelrahman_alsayed@yhaoo.com

    thanks,
  39. 0
    Dave Morrow ·
    Me to please

    david.morrow@echarris.com


    Thanx
  40. 0
    Henry Odili ·
    Hi
    can you please send me a copy of the planning and scheduling procedure to my email address.odilihenry@yahoo.com
    Thanks
    Henry
  41. 0
    Cleetus Pankiras ·
    Can somebody please send me a copy of planning & scheduling procedure ?
  42. 0
    Carlos Chavez ·
    Me to please

    jcchavez@dcidp.pemex.com

    Thanks
  43. 0
    Sue Chambers ·
    Could I also have a copy of the procedure

    Send to suejc1@hotmail.com
  44. 0
    Hans Masuy ·
    hi everybody,

    actually i’m looking for a planning and scheduling procedure, a comprehensive one if possible. My planning department is trying to develop our own procedure for future purpose.

    thanks.

    H.M
    Project Manager
  45. 0
    Hans Masuy ·
    ahmet cetin,

    thanx pal. appreciate so much.
  46. 0
    Wanyong Li ·
    Hi Guys,

    could you send me a copy of EPC scheduleing and planning procedures?

    Best Regards,
    Wan Yong
  47. 0
    Wanyong Li ·
    Hi Guys,

    could you send me a copy of EPC scheduleing and planning procedures? email: liwanyong@163.com

    Best Regards,
    Wan Yong
  48. 0
    Julius Calantas ·
    Please can I have a copy also.

    juliu2532@yahoo.com
  49. 0
    Jay Samortin ·
    Hello everyone... can i ask for a copy also.

    jay.samortin@gmail.com

    thanks in advance!
  50. 0
    Shah. HB ·
    Hi

    Links mentioned in this forum found be worthily.Thanks to all