Resource Planning
In the Open Standard
SK
Siva KumarMember for 21 years 3 months
- Created
- 81
- 10
0
81 replies
Oldest first- 0VLVladimir Liberzon ·Anoon,
these are activity requirements:
1. The quantity of work is measured by single physical unit,
2. The same crew is doing the work from the beginning to the end,
3. Productivity is the same from the beginning to the end (if external conditions are the same - season, weather),
4. The payments are the same (for an hour or volume unit),
5. Activity belongs to the certain work package,
6. Activity duration is reasonable, in accordance with the period of schedule analysis (40 hours rule is an example), but this is optional if the quantity done can be measured in physical units.
In this case you will be able to apply the norms - production norms, unit costs, material requirements per volume unit and you will be able to prove that your schedule is created basing on the corporate or inductry standards. It is not easy to justify the schedule that is based on somebody’s vision. - 0RMRodel Marasigan ·Anoon,
My understanding of detail is these: For Reinforced concrete works (i.e. Foundation) you have different work forces required to complete the job. You need work force for excavation, another for carpentry works, steel man for reinforcing and Mason and laborer for purring of concrete. This required different task to get the correct workforce to level.
Say: m3/hr for excavation (machine and operator), m2/ hr (carpenter, labor for formworks), ton/ hr (steel man), m3/hr (Mason, laborer, equipment and operator).
If the said Activity is not detailed to task how can you get the correct workforce required when you level the resource? - 0MDMimoune Djouallah ·thanks all for your valuable input
Rodel you catch exactly what i want to achieve, once i get the needed productivity of concrete work to be done to respect the said milestones, it is up to the contractor to manage his resource to respect those duration. after all it is up to the contractor to manage his resources.
and for resource leveling, Vladimir i absolutely disagree;)( at least that’s what i notice from my little experience)
that’s depends on the planner background, if he started work from the contractor side, it is the first thing that he cares about,but if he had only work for the main contractor, generally they tend to think that resource are unlimited or that it is the problem of contractor not them.
best regards
- 0MDMimoune Djouallah ·thanks all for your valuable input
Rodel you catch exactly what i want to achieve, once i get the needed productivity of concrete work to be done to respect the said milestones, it is up to the contractor to manage his resource to respect those duration. after all it is up to the contractor to manage his resources.
and for resource leveling, Vladimir i absolutely disagree;)( at least that’s what i notice from my little experience)
that’s depends on the planner background, if he started work from the contractor side, it is the first thing that he cares about,but if he had only work for the main contractor, generally they tend to think that resource are unlimited or that it is the problem of contractor not them.
best regards
- 0MDMimoune Djouallah ·thanks all for your valuable input
Rodel you catch exactly what i want to achieve, once i get the needed productivity of concrete work to be done to respect the said milestones, it is up to the contractor to manage his resource to respect those duration. after all it is up to the contractor to manage his resources.
and for resource leveling, Vladimir i absolutely disagree;)( at least that’s what i notice from my little experience)
that’s depends on the planner background, if he started work from the contractor side, it is the first thing that he cares about,but if he had only work for the main contractor, generally they tend to think that resource are unlimited or that it is the problem of contractor not them.
best regards
- 0AIAnoon Iimos ·Mimoune,
Thanks for digging up up this three year old thread, and it seems that until now, it is not understood on where "Resource Planning" can be applicable?
And they said, resource planning can only be applied if your schedule is "detailed" which means measurable, adjustable and corresponds to other variables.
So what is the level (level 3,4,5...) of this so-called "detailed schedule" wherein you can practically assign and adjust resources?
Would this mean as well that for level 1 or 2 schedules (representing only work packages), you can never expect to assign resources (practically) or make whatever adjustments as regards resources? - 0VLVladimir Liberzon ·Mimoune,
I don’t understand with what you disagree.
The owner may think that contractor’s resources are unlimited and it means that he does not level resources at all and can use less detailed schedule that sets contractual milestones.
But clever owner will try to set the requirements to the contractor resources and to control if the contractor workforce is sufficient for proper project performance.
Anoon,
usually the resource loaded schedule is considered at level 4 or even 5. But I don’t approve these levels. The schedule can be shown with different details but if instead of one you manage several schedules of the same project it is hard to avoid errors and besides it is a lot of unnecessary work.
Best Regards,
Vladimir - 0RMRodel Marasigan ·Anoon,
Majority of the company that I work with are having this practice. When the company submit a bid having a schedule of level 2 or 3 resourced and cost loaded as required. This will include critical path, identified risk, S-curved and histogram but management level. Meaning the resources are not breakdown as detailed but showing the total number of workforce from start to peak to finish.
When Project start the planner start to derive the baseline from the level 3 down to manageable level of details that the project required to handle all the scope as per submitted schedule on the contract (level 4 or 5 will be created with the same critical path) and resubmit for approval. Resources are more detailed and more defined and a cost account has been created as per WBS but more detail. All unknown scope but already have budgets are separate and not included for BAC until it’s been identified and added to the baseline. (Mostly provisional sum and management reserved). These levels of detail are useful for what if scenario and conditions required needed to be meet. - 0MDMimoune Djouallah ·Vladimir
i can’t disagree with you ;) i want just to say that planner who worked before as supervisor or in generally worked as contractor (the guy who really do the work in site) are very aware about the importance of resource leveling, i think it is very obvious, work completion depend on resource deployed.
Anoon.
we level at level 3 (it may be level 4 for other definitions); work package, let’s say compressor foundation for civil we put only two activities excavation, and concrete work, ( notice here concrete work is reinforced concrete, the steps , re-bars, formworks, pouring, foundations protection are considered for assessment of progress but not for planning)
now we assign resource concrete work with a unite rate of say 10 m3/day and the total quantity 500 m3 ( notice here it is equivalent quantity, concrete + rebards)
we do the same for all the packages.
we assign a normal and max usage for the resource, and schedule and level.
once we have the durations, now the hard part, the contractor must level his resources to respect those durations, he may further develop a more detailed programs ( put the real activities rebars, formwork, pouring with real resources labor, batching plant..), or use traditional method, ask field supervisors how each one need labors and equipment to finish the package in time, it is very interesting experience to see supervisors fight over resources (actually i attended a real fight about that;)
best regards
- 0TRTrevor Rabey ·Mimoune,
I am with Vladimir on this one.
If you simply dictate some durations and then say that it is the contractor’s problem to manage his resources, you can be sure that his problems will become your problems.
If you don’t bother to work out that it takes 17 tilers to lay the tiles in 20 days, how will you know that he knows how to manage that, and how will you know that if he turns up with 3 tilers every day the task will be late? When will you know? You won’t know until day 20 has gone by. Of course you can sue him but that won’t get your project back on schedule and 20 days has gone, never to return. - 0AIAnoon Iimos ·Trevor,
I supposed the Client or Owner is not "dictating durations", but I believe they are guessing durations and let the Contractors validate that guess.
So why the Client should bother about how many tilers the Contractor is supposed to assign? When all the Client wants is a Tile this much, and to be finished or delivered on this time?
All the rest, you can refer to the Contract.
- 0TRTrevor Rabey ·"So why the Client should bother about how many tilers the Contractor is supposed to assign?" because if he doesn’t bother about it, either making sure that the contractor has it figured out, or doing it himself, then his project will be late.
If it turns out that the client has not done it, often the contractor doesn’t do it, because he can’t, then no one has done it.
The client can want and wish or hope for anything he likes, but he won’t get it unless someone figures it out.
You may think that this doesn’t happen, that the client just leaves it to the contractor, and the contractor doesn’t do it, and the client never properly investigates to discover it. But it does happen, Ive seen it. - 0AIAnoon Iimos ·Happy Easter to All,
Question(s):
Activity Requirements vs. Resource Requirements
or Activity Planning vs. Resource Planning
1. Which comes first?
2. How is it related or what is the relationship between activity and resource?
3. Who’s responsibility is what? or i.e. Who is the primary responsible to prepare the Activities (Work Packages / Milestones) and/or Resources? The Client/Owner or the Contractor?
4. What is most important? Activity sequencing? or Availability of limited Resources (including Calendars, other Constraints)?
Please answer by instinct without considering any form of Contract.
Thanks - 0VLVladimir Liberzon ·Hi Anoon,
activities require resources to performed.
Activities are planned first - you shall decide what to do first and then who will do what.
If necessary resources are not available activity performance will be delayed.
The Client/Owner define the requirements to the project schedule, Contractor developes the schedule.
The schedule shall respect all constraints - activity sequencing, resource availability, Calendars, everything.
Best Regards,
Vladimir - 0AIAnoon Iimos ·Hi Vladimir,
"Activities are planned first" - What’s the consideration here? Highest priority (meaning Activities sequencing will drive the schedule - first)?
"The schedule shall respect all constraints - activity sequencing, resource availability, Calendars, everything."
Order (I’ll limit to three):
1. Activity(s) sequencing
2. Resource Availability
3. Calendars - (might involve both Activity and Resource)
For number 3, which one should be considered first, Activity Calendar or Resource Calendar?
You might say that it will depend if your Schedule is Task Dependent or Resource Dependent, but please remember, "Activities are planned first".
Hi Mike,
Would you mind answering with substance?
Best regards
- 0AIAnoon Iimos ·Vladimir,
Re:"The Client/Owner define the requirements to the project schedule, Contractor developes the schedule."
What do you mean by requirements? Up to what level of specifics (generally)?
Please don’t say, depending on the contract.
I supposed "Resource(s)" for the Client/Owner will be the Contractor, Permanent Materials and Permanent Equipment.
How does "Resource Planning" for a Time Schedule relates or affects the Client/Owner?
Best regards - 0VLVladimir Liberzon ·Anoon,
I will answer basing on Spider Project functionality but will omit the usage of typical fragment library. We shall discuss it later.
1. Start with the results WBS. Work packages in this WBS mean achieving some small result.
2, Decompose work packages creating project activities (describe actions that shall be done to achieve corresponding results.
3. Link activities of work packages and then enter links between activities of different work packages. Add and link milestones.
4. Enter activity types - some of them are duration driven, but for most their durations are defined by the quantity of work and assigned resource productivities. Enter activity types.
5. For duration driven activities enter expected durations, for others enter the volumes (quantities) of work to be done.
6. If absent, create a list of project resources and enter their quantities.
7. Define activity and resource calendars. Activity calendar defines the periods when it can be performed. Resource calendar defines resource work periods. Activity can be performed only when the time is working for all calendars - activity can be performed and assigned resources are available.
8. Create crews - groups of resources necessary for doing the work on different activity types. We call these groups multi-resources.
9. Assign crews (it means assigning all crew resources). If resources shall work only together they belong to the same team. If resources can work independently assign them as the separate team.
10. Enter productivities of assigned resources for those activities whose duration is defined by work quantities.
11. Create a list of materials.
12. Assign materials to activities and resources (fixed quantities, or quantities per hour, or work volume units).
13. If materials are restrited create the supply schedule (when and what material quantities will become available).
14. Now you are ready for scheduling.
The better way for creating schedule model - use typical fragment library and corporate reference-books. But this is Spider Project specific.
Let’s return to calendars.
There are separate activity calendars (when activity can be performed), resource calendars (resource work time), and dependency calendars (applied to dependency lags).
Activity will be performed at periods when the time is working for both activity and all resources assigned in the same team.
If resources do not belong to the same crew and can work on activity independently then they shall be assigned as different teams.
Best Regards,
Vladimir - 0VLVladimir Liberzon ·Yes,
For Client/Owner resources may be Contractors, main Materials and Equipment, but the Client may require from the Contractor to submit the resource loaded schedule with certain WBS and level of details. It is required because the Client wants to be sure that the Contractor understands the job, plans it properly, and have sufficient resources to finish it on time. It may be used for the control if the quantity of resources on site is sufficient.
Best Regards,
Vladimir - 0AIAnoon Iimos ·Hi Vladimir,
I supposed when the Client/Owner accepts the Contractor, that means that the Contractor is qualified for the job.
And I don’t believe that the ability to prepare a proper schedule (resource loaded), is one of the basis for Contractor’s pre-qualification (maybe), but I supposed they are not counting on that in the first place.
The Client/Owner will give the Scope and the specifications (in general), but would they dictate about the methods of the Contractor?
Best regards
- 0RMRodel Marasigan ·Anoon,
If you read my post #63, it clearly stated that activity first before the resources for most of the projects.
1) When preparing a schedule for a bid documents, resources are on summary level on the schedule because the detail task was not yet created as per construction methodology but the schedule represent the whole scope in the contract.
2) Once the project is commencing or awarded, the PM will resource the project with the help of planner, estimator and HR. The planner will breakdown the schedule into manageable detail and start resource planning with the help of construction manager based on construction methodology and submit to PM for approval.
Hope this answer you question. - 0AIAnoon Iimos ·Hi Vladimir,
"And usually the Contrator shall submit resource loaded schedule in the certain period (like 30 days) after the contract was awarded." And I may add, for Client/Owner’s approval (or record only?)?
The question here is, Can the Client dictate the "resource planning" of the Contractor based on its methodology (if ever the Client don’t like or does not approve the schedule)?
Hi Rodel,
"Activity first" - so which calendar governs (in case of conflicts), activity calendar or resource calendar?
Best regards - 0RMRodel Marasigan ·Anoon,
In general practice Activity calendar first. It will give you the full duration of the job. Resource calendar will take place if the delay occurs where you need to plan your resource to catch up the delays. This is where the PM decides to have 2 shift or accelerations of resources. This will depends on working area, safety & environmental issues and risk management. If the area is too crowded for increasing the resource productivity will become an issue including safety and risk that is why shifting of works are considered. While considering the shifting, safety, environmental and risk is again analyzed if the area is recommended for double or triple shifts. Again if not possible then working extra hour maybe appropriate.
Is that making sense? - 0VLVladimir Liberzon ·Hi Anoon,
the Client dictates the requirements and can reject the schedule that was submitted if it does not comply with the requirements.
In Spider Project the work can be done during those periods that are working in both activity and resource calendars.
Activity calendar set restrictions on activity execution (like only on Summer, or during the day time), resource calendar defines the work time of the resource. It does not matter which one is first.
Vladimir - 0AIAnoon Iimos ·Hi Rodel,
Yes, but I mean considering calendars of limited resources (no consideration of unlimited resources - as where your activity calendars were supposed to have been derived).
Meaning you got to decide between your activity calendar and resource calendar knowing that if you use resource calendar, your schedule (duration) will certainly extend, therefore creating further problems.
I supposed Vladimir’s Spider was designed to handle limited resources on large scales projects?
Best regards - 0VLVladimir Liberzon ·Anoon,
calendars show when the work can be done. It does not make sense to ignore non-working periods.
I see the problem if our approved schedule is unrealistic.
Yes, Spider Project can handle limited resources for huge projects, programs, portfolios.
Best Regards,
Vladimir - 0RMRodel Marasigan ·Anoon,
When binding to a contract, a milestone is set and it may link to LD for most of the cases. This is why activity calendar is first to meet the milestone. If activity calendar is not visible due to resource restriction then it should be brought up to the client to approve the new milestone date. If client insist the original milestone, the contractor or PM will now decide and re-do the resource planning to meet the milestone for as far as he can get. That is why more resources are coming from overseas.
I hope this answer you question.
Log in or join to reply