Has anyone a definition for "Burn Rate"?

3 replies

Oldest first
  1. 0
    Rizwan Ahmed Siddiqui ·
    Burn Rate: The rate at which cost or man-hours are being expended on a project. or we can say how much money/time/resources are we using in this effort/project?

    Rizwan
  2. 0
    Brennan Westworth ·
    That is correct... it is usually expressed as $ or Mhrs per day / week / month
  3. 0
    Marcio Sampaio ·
    Burn rate is a synonymous term for negative cash flow. It is a measure for how fast a company will use up its shareholder capital. If the shareholder capital is exhausted, the company will either have to find additional funding or close down.

    The term came into common use during the dot-com era when many start-up companies went through several stages of funding before emerging into profitability and positive cash flows and hence becoming self-sustainable (or, as for the majority, failing to find additional funding and sustainable business models and hence going bankrupt). In between funding events, burn rate becomes an important management measure, since it together with the available funds provides a time measure to when the next funding event needs to take place.

    Some claim, that part of the reasons behind the dot-com bust, was the unsound management and financial investor practices to keep the burn rate up, taking it as a proxy for how fast the start-up company was acquiring a customer base.

    Aside from financing, the term burn rate is also used for projects to determine the rate at which hours (allocated to a project) are being used, to identify when work is going out of scope, or when efficiencies are being lost.

    Regards.