PIPING SCHEDULE

Shaunna InksMember for 19 years 6 months
Created
4
3
0
Hi, experts, ’am new in scheduling, was asked to do detailed schedule on mechanical piping in a refinery, can anyone point me to where I could get a sample work breadown structure on piping? I checked the summary schedule and only shows a 1 line activity mechanical piping installation. can anyone help? I appreciate any info!

4 replies

Oldest first
  1. 0
    Anoon Iimos ·
    check your drawings, specifications and methodologies and apply it
  2. 0
    Shaunna Inks ·
    Thanks, Anoon, I was just given a list of the piping spools, total and , with engineering dwg fabrication dates, ship dates, rec’d on site... but i need to look at a construction methodology, any samples?. thanks again!
  3. 0
    Rodel Marasigan ·
    Hi Shaunna Inks,

    For Piping usually track as follows.

    Piping Fabrication
    1) Handling
    2) Prep/ Fit-up of spools
    3) Welding/ Jointing
    4) NDT
    5) Painting (Optional/ it can be site painting)
    6) Delivery on Site

    Piping Instalation
    1) Handling/ Set-up in place
    2) Jointing (Welding, Screwed, Bolt-up)
    3) Valves/ In-line items installation
    4) NDT
    5) Support/ Hanger
    6) Painting/ Touch-up paint
    7) Insulation (Optional)
    8) Hydrotest
    9) Punch list

    Commissioning also required but it should be separate WBS as it has their on task/ activities.

    Regards,
    Rodel
  4. 0
    Shaunna Inks ·
    Hi, Rodel! Salamat!
    I will email you the stuff that was given to me, and I don’t know where to start.....
    thank you again.
    Regards,
    Shaunna

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?