Project Tracking (Schedule & Cost Performance)
In the Open Standard
Hernando PescaMember for 19 years 5 months
- Created
- 5
- 3
0
Fellows,
What is usually the acceptable cost performance index (CPI) and SPI? Currently, our project (a manufacturing plant) in Bahrain has a CPI of 1.28 (the highest we have) and SPI of 1.02.
If the CPI goes higher, the schedule is very conservative and the baseline is a "poor baseline". In your experience, what is the highest CPI you have? What corrective measures are you taking? Are you revising the schedule?
Thanks...
Hernan
What is usually the acceptable cost performance index (CPI) and SPI? Currently, our project (a manufacturing plant) in Bahrain has a CPI of 1.28 (the highest we have) and SPI of 1.02.
If the CPI goes higher, the schedule is very conservative and the baseline is a "poor baseline". In your experience, what is the highest CPI you have? What corrective measures are you taking? Are you revising the schedule?
Thanks...
Hernan
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?