long lead delievery items schedule

Bilal TirmiziMember for 17 years 10 months
Created
4
2
0
Can anyone please explain the concept of Long lead Delievery items schedule

In developing such a schedule whic things to be considered
what information it shall give
which items shall be considered in developing it
in which format it shall be like in primavera or excel

and if some one has on such schedule , please send me for sample

my email id is bilal_tirmzi@hotmail.com

4 replies

Oldest first
  1. 0
    Ashutosh Nema, PMP ·
    Dear Bilal,
    Most important aspect in Long lead items are the manufacruring time,shipment and custom clearance(if applicable).
    You can make this schedule in Excel as a Procurement schedule and put duration from tender preparation to delivery on site+time for inspection in Primavera shedule.
    Items related to MEP are mostly the long lead items.

    Regards
    Ashutosh
  2. 0
    Bilal Tirmizi ·
    Thanks Ashutosh
  3. 0
    Samer Zawaydeh ·
    Dear Bilal,

    You will need to review your Electromechanical Contract requirements in particular.

    Usually long lead items include systems like:
    Lifts
    Kitchen & Laundry Equipment
    Lighting Fixtures
    Low Current systems
    HVAC equipment
    Fire Fighting Pumps
    Generators and Package Units.

    If you are importing Finishes works, then you will need to check on the approval, manufacturing, delivery and custom clearing procedures.

    It is always advisable to have all the information in one place in order not to forget bits and pieces. So include you long lead items in your Procurement Section in your Main Schedule and link it to Material submittal and to the start of Construction.

    Good luck,

    Samer
  4. 0
    Bilal Tirmizi ·
    THANKS SAMEER

    IT WAS VERY HELPFUL