Schedule for Road Utilities

Pacifico PallasiguiMember for 22 years 8 months
Created
1
3
0
Planners,


Can any body could share some schedules for road utilities like water relocation, stormwater relocation, irrigation, sewer & telephone these utilities will relocated because we will be building Road Tunnel here in UAE.


Thanks

Pacifico

1 reply

Oldest first
  1. 0
    KS Wong ·
    Hi Pacifico,

    there are some typical activities for your reference.

    1. ELS Design Submission & Approval
    2. Temp. Traffic Arrangement Submission & Approval
    3. Design submission & Approval by Utility Undertakers
    4. Excavation Permit Application & Approval
    5. Trial pits
    6. TTA Implementation
    7. ELS & Excavation
    8. Existing Utilities Diversion / cut-off
    9. Relocation of Utilities
    10. Backfilling & Reinstatement
    11. Repeat steps 6 to 10 if more than one TTA stage.

    Regards,
    KS