Skip to content

Infrastructure Schedule ! ( Raods,sewerage,..etc )

Amr DiabMember for 19 years 8 months
Created
3
3
0
Hi Everyone,

I was asked to prepare an infrastructure schedule having the following:

1- Road Works
- Geo-Tech Investigation
- Road Works
- Channel Crossing
- Storm Water Drainage
2- Infrastructure
- Sewerage Works
- Street Lighting
- Telecommunication
- Potabel Water System
- Irrigation and Fire Fighting System
- HV & LV Distribution Network

As i have no previous experience with these projects, i just want to know the logical sequence or the link between these trades.

please let me know about any consideration I should take also .

Thanks,

Amr




3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Amr,

    In three minutes of less,

    1. Both will have the following logical sequence.

    I. Soil Investigation.
    II. Design Drawings.
    III. Site Survey.
    IV. Material Submittals
    V. Shop drawings submittals
    VI. Material procurement.

    2. In more details:

    Road Works
    1. Complete cut and fill
    2. Fill in layers and testing
    3. Install services (E/M)
    4. Complete wearing surface (Asphate, Interlocking, concrete)

    Infrastructure:
    1. Complete Mechanical works
    2. Complete Electrical works.

    You will need to get with your team members and create the WBS for the works. It depends on the scope outlined in your contract.

    With kind regards,

    Samer
  2. 0
    Mike Testro ·
    Hi Amr

    With linear projects such as roads and pipelines the work progresses along the chainage so the sequence that Samer has descibed will have to be repeated in sequence along maneageable lengths of the road.

    A key factor is the planning and sequencing of haul roads for cut & fill - particularly if they are on the carriageway.

    Another consideration is that drainage pipes are generally laid "Up Gradient" which may be contrary to the flow of work for the other tasks.

    I would suggest the use of Tilos software for such linear projects although a similar effect can be gained by using PowerProject in "Task per Line" mode.

    The main rule in planning is that if you don’t know how to build ask someone who does - not just fromm PP but somenoe nearer your project.

    Best regards

    Mike Testro
  3. 0
    Marwan Ibrahim ·
    WBS:

    1. TRADE
    2. AREA
    3. ROAD NAME (STATIONS)
    4. DEPTH RANGE (DEEPER LINES ARE EXCAVATED FIRST)

    ACTIVITIES:
    1. EXCAVTION/TRENCHING
    2. BEDDING/SURROUND
    3. PIPELAYING
    4. INITIAL BACKFILLING
    5. TESTING
    6. FINAL BACKFILLING

    ENJOY PLANNING.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?