DAMS (Hydro Project Management)

R. Onur YAZICIMember for 19 years 1 month
Created
5
4
0
I need to prepare a draft schedule for a mid-sized dam project. Since I have no experience in that area, I need help from my scheduler friends ..

Could you pls post activity list of a dam project or I’d really appreciate if you could post a sample file as well.

Thanks.

5 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear R.,

    Dams are constructed in several ways. The scope should be clearly defined in your Bill of Quantity, and the Construction Method can be figured out using your team members.

    You can google the internet. A 1st search yielded the following site:

    http://www.ussdams.org/02pm.html
    "Dam Construction Project Management Guidelines"

    You can divide the works into two sections:
    1. Substructure
    a.soil stabilization
    b.earthworks
    c.civil works
    d.Electromechanical works

    2. Superstructure
    a. Civil
    b. Mechanical
    c. Electrical Works

    Testing and commissioning of course is needed upon completion of the works.

    If you have any specific questions, we might be able to help.

    Best Regards,

    Samer
  2. 0
    Cemran Kirkpinar ·

    Dear Samer, Actually this

    Dear Samer,

    Actually this topic is not the one i was looking for, but i think in many ways its related to the samples that i need. I am quite a rookie in that area so i need samples of WBS for a HE Project in Renewable Energy.

    If you have that kind of information, i would be grateful if you can send it to me at use private message service Many Thanks,

    Cemran

  3. 0
    Gary Whitehead ·

    Cemran,   It is not good

    Cemran,

     

    It is not good forum manners to reply to a post which is 2 years old in order to ask for information not related to that post. Please post such requests in a new topic.

     

  4. 0
    Cemran Kirkpinar ·

    Mr. Whitehead,I am sorry but

    Mr. Whitehead,

    I am sorry but its just sometinng i googled and the search engine come up with this topic, thats why i posted this message, if i had found a newer topic i would have posted to that one anyway..

  5. 0
    Mike Testro ·

    Hi Cemran Welcome to planning

    Hi Cemran

    Welcome to planning planet

    The best Idea is to start your own new topic in the relevant forum.

    It is possible that contributors to an earlier thread have ticked a box to get an email whenever someone responds to their question - now they are getting pinged from your topic.

    As Gary said - its not good manners.

    Best regards

    Mike Testro

Log in or join to reply