Basis of schedule

Willem PrinslooMember for 17 years 3 months
Created
12
4
0
Afternoon,

I were asked to generate a Basis of Schedule document by my client. I have never done this and would like to know if someone can help me with a template.

12 replies

Oldest first
  1. 0
    Anoon Iimos ·
    well, never done it too but anyway let’s try to start with:

    1. Scope of Works? (what if still in the concept stage?)
    2. Contract? (same question)
    3. Drawings / BoQs? (again, the same question)
    4. Methodologies? (")

    sorry
  2. 0
    Willem Prinsloo ·
    We are finishing the class 3 study and one of the deliverables is a basis of schedule document for the construction phase. I presume it is like a basis of estimate document for the schedule
  3. 0
    Anoon Iimos ·
    say for example: you are tasked to do re-engineering of an existing plant, what would be your deliverables? and how are you going to schedule it?
  4. 0
    Ernesto Montales ·

    Try the following links this explains the concept of Planning for the Schedule. It’s from the PMI College of Schedulling.

    http://www.pmicos.org/ondemandlearning.asp

    PMICOS - Scheduling with the Masters - Jul. 16
    Topic #1: Planning for Schedule Development

    Cheers,

    Ernesto
  5. 0
    Shah. HB ·
    hi

    do we have to give narrative of pro gramme of works to client ?
  6. 0
    Willem Prinsloo ·
    No I don’t think we have to give narrative. I will get more information
  7. 0
    Anoon Iimos ·
    Willem,

    May I refer to your post # 3, you mentioned that you are required to submit as one of the deliverables - a Basis of Schedule for Construction Phase.

    Well, I supposed you were refering to Engineering Documents + Procurement (if any) + Site Investigation Reports.

    Are there any other ways to create a Construction Schedule without referring to the above-mentioned documents?

    cheers
  8. 0
    Anoon Iimos ·
    I would like to add as "Basis for Schedule":

    1. Strategies

    2. Methodologies

    3. Available Resources

    And sometimes we cannot deny that we are making schedules without any basis. A list with corresponding lines, sometimes is enough.

    cheers!
  9. 0
    Christian Adrian De Vera ·
    Willem

    Try searching the AACEI website, look for the recommended practice No. 38R-06. This might give you an idea.

  10. 0
    Willem Prinsloo ·
    Thanks. That document will help. Now I got a good idea of what to do
  11. 0
    Brikey Don ·

    Would anyone be able to give

    Would anyone be able to give me sample Basis of Schedule ? Much Appreciate.

    regards,

  12. 0
    Brikey Don ·

    Would anyone be able to give

    Would anyone be able to give me sample Basis of Schedule ? Much Appreciate.

    regards,

Log in or join to reply