Waste Water Treatment Plant Schedule

Izam ZakariaMember for 20 years 4 months
Created
2
3
0
Guys,

I’m just wonder if I can learn a little bit on subjected above. Is it any one of you can share me the common activity of Waste Water Treatment Plant Schedule.What is typical critical activity if you don’t mind to share it with me. If you have attachment I can be reached via aizam.zakaria@yahoo.com

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    It depends on the design and locations of Waste Water Treatment Plant.

    Critical activities varies on design, lead procurement items like mechanical equipments, aerators, pumps, cables, generators, clarifiers equipments, grit & screen, piping materials, structural, handrails, platforms, tanks, media filters,valves,Penstocks & Stop Boards, SCADA, PLC, Switchboars etc … and construction methodologies and commissioning, service proving, operator trainings and many others.

    If designs consist of Waste Treatment plant, Recycle Treatment, Class A & Class B storage tank or lagoon then all of those have different criticality, especially on long lead items that mostly takes 3 to 6 months and if not available in the country then it will take more if coming from overseas.

    Typical Items are:
    A) Common Facilities:
    1.     Earthmoving
         Bulk Earth works & Earth moving & backfill
         Landscape
    2.     Civil Works
         Roads and pavements
         Roads Hardstand & Guardrails
         Permanent Fencings
    3.     Mechanical Works
         Some mechanical equipments
         Underground piping
         Potable water piping
    4.     Electrical & Communication Works
         Lighting Protections
         Area, Road Lightings & Flood lights
         Site lighting and small power
         Security Access & CCTV System
    B) Waste Treatment Plant and buildings
    1.     Inlet Structure
    2.     Screening & Grit
    3.     Balance Tank, Bioreactor & WAS pump
    4.     Blower
    5.     Clarifiers
    6.     RAS Pump Station
    7.     Dual Media Filter & Filtrate Storage
    8.     Waste Buffer Tank & Pump Station
    9.     Chorine Contact Tank
    10.     Chemical Storage & Unloading
    11.     Lime Storage & Unloading
    12.     GPPS & Tanker Receival Pump Station
    13.     Tanker Receival Facilities
    14.     Electrical Building and Facilities
    15.     Sludge Dewatering
    16.     Odour Control Facilities
    17.     Control Buildings
    18.     Workshops
    19.     Tanker Loading Area

    If Recycle water treatment plant is also included then another major items like Ultra Filter, Switch room, UV disinfections etc…
    It may include Storage tanks or lagoon and Pump Stations.

    Hope this help.

    Best Regards,
    Rodel
  2. 0
    Izam Zakaria ·
    Rodel,

    Thanks for your explanation buddy.Good enough for me to apprehend the process flow.