Consolidated "Master" Schedule
- Created
- 9
- 6
Hello all,
A Project Management company I do work for , has been hired in a project midway in the Design Phase (Actually at the start of Design Development phase). I was tasked with "consolidating" 2 different schedules.
One seems to be titled "Master Schedule" and was distributed to different cost /light and technical consultants with their tender documents. The other one is the "contractual schedule" included in the contract agreement with the Main Design Consultant.
For some reason, the Owner did not bother to include the so called "Master Schedule" in the Design Consultant's tender Package and obviously enough the resultant "contractual schedule" contains at times diverging logical links and so on.
In My understanding , you're supposed to include the Master Schedule (created at planning stage) in every package so that each contractor/consulting takes into consideration how his schedule links in to other project participants work.
The issue I am having is that the critical path on the DC designer schedule is not preserved in the resulting Master Schedule for obvious reasons.
Note that both schedules having to be consolidated were not properly built and contain grave errors.....
Anyway , how would you proceed in such a situation?
9 replies
Oldest firstLog in or join to reply