Do you think this is a proper way to update a schedule?

Carlos AranaMember for 17 years 4 months
Created
6
3
0

Recently, a colleague sent me the link to this game:

http://thatpmgame.com/

Is this really how Project Managers from around the world are updating their schedules?

I think that if an activity in the critical path is not being advanced as planned, the schedule update should show the impact on  the finish milestone.

What do you think?

6 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    Carlos, this approach is

    Carlos,

    this approach is certainly wrong but supported by MS Project.

  2. 0
    Trevor Rabey ·

    Vlad, let's assign the blame

    Vlad, let's assign the blame to the people who don't bother to understand the tool or use it properly, rather than the tool.

    Ok, so it is very wrong in many ways. The original plan is wrong and so also is everything to do with the tracking. Let's discuss why.

  3. 0
    Vladimir Liberzon ·

    Hi Trevor, I did not blame

    Hi Trevor,

    I did not blame the tool. I just wrote that MS Project supported this approach to project tracking and this is one of the reasons why it still exists. The way of tracking does not mean that original plan is wrong (or right). I understood the question as the question on project tracking and control methodology.

  4. 0
    Tanveer Ahmad Niazi ·

    Hi all planners, I am quite

    Hi all planners,

    I am quite new in planning. In P3 it was not difficult for me to get the cash flow, please don’t make a joke of me, but in P6 I am not able to get cash flow even after a year working on P6. Please give some hints or advice.

    Tanveer

  5. 0
    Carlos Arana ·

    The activities without

    The activities without predecessors or successors are also a common error, but most errors during the schedule creation phase could be avoided if the schedule team had clear how will the schedule update and what will be its behavior.

    It would be good if there existed an animation showing how will the schedule behave when it is updated.  It would help us schedulers to explain why the links are as important as the bars.

  6. 0
    Anning Sofi ·

    Nope. That is just a game.

    Nope. That is just a game.