Schedule Calculations

Patrick WeaverMember for 25 years 8 months
Created
1
4
0

There are a range of options for the calculation of dates and float in a CPM network.

I’ve just finished a draft White Paper focusing on the basic calculations and would appreciate comments on the correctness of the calculations and the methodology adopted.  The aim is to produce a definitive document that is generally agreed. 

You can download the paper from http://www.mosaicprojects.com.au/PDF/Schedule_Calculations.pdf  All comments gratefully appreciated.

1 reply

Oldest first
  1. 0
    Puneet Gupta ·

    Patrick:Your approach for

    Patrick:

    Your approach for calculation is not correct, You are missing the basic fundamentals.

    Also, your Formula "EST = Preceding EFT + [Lag + 1]" is very general. What if I finished Activity A at 18:00 hrs of Day 2 and I am in a position to start Activity B on same day at 18:30 hrs?

    On Page 7 of 17 (BackwardPass Calculation) , I could not understand how did you get the LFT for Activity B as 14 and not 11?

    In general,

    ForwardPass Calculation:

    EFT = EST + DUR - 1

    BackwardPass Calculation:

    LST = LFT - DUR + 1

    Regards,

    Puneet Gupta

    Bau Management + Consulting GmbH

Log in or join to reply