What is the sequence to create the project for Electrical control room

Kumar BaijuMember for 15 years 8 months
Created
6
6
0

Hi

  I want to create the project control room. here i want to know that what is sequence of activity.For example

1. Concept Note by Electrical department

2. assignment drawing to Civil & Structure, HVAC, Instrument

3. HVAC gives the assignment to CIVIL

and so on...

 

Can any one suggest the site where i can get son standard procedure or guide for sequencing to engineering project

 

Thanks in advanced

 

Regards'

KBJ

6 replies

Oldest first
  1. 0
    Syed Ali ·

    Kumar, Little confused with

    Kumar,

    Little confused with your question. Are you going to develop a Schedule for new Control Room or what?

    Please clarify.

    Regards,

    SE Ali

  2. 0
    Kumar Baiju ·

    Dear Ali   Yes . i want to

    Dear Ali

      Yes . i want to develop a new schedule for a control room (containing electrical, instrument panel, DCS Panel, electrical circuit breaker etc).

     

    regard\\

    KBJ

  3. 0
    Gary Whitehead ·

    assuming the control room is

    assuming the control room is to control new equipment, the design / procurement / construction sequence would be something like:

     

    1) datasheets / specs for new equipment to be controlled

    2) let orders for the same

    3) vender details of the same back, including loading

    4) spec for DCS / MCC / etc

    5) let orders for the same

    6) vender details of the same back, including sizing & ventilation requirements

    7) HVAC design (if required)

    8) Civils design

    9) Civils construction to weatherproof

    10) M&E installation

     

    NB: This can be quite a length process as you have to design & order all your plant before you can start design on the control kit. If time is a factor, another option is to start HVAC and civils design & civils construction before the control kit is ordered, and over-engineer the solution to ensure it will be adequate (ie a bigger room than you think you'll need with more HVAC than you think you'll need). Obviously more expensive this way, but MCCs are often on the critical path of process projects so it can be worth it.

  4. 0
    Kumar Baiju ·

    Many many Thanks GARY

    Many many Thanks GARY

           In the next topic i want to know Compressor House Building Schdule.

     

    Regards\\

    KBJ

  5. 0
    Stella Lewis ·

    Winsted Worldwide Control

      Winsted Worldwide Control Rooms 

    www.winsted.com  Main (0) 1905 770276

    Winsted Corporation has over 46 years experience in providing quality control room furniture solutions.  Serving security, video, traffic, utility and defence control rooms world wide.

     

    Winsted’s products, installation operations, and services are tailored specific to your requirements.  Whether you need a single workstation, or a complete control room, we can provide the perfect solution. At Winsted we are pleased to offer you a Free design service to provide you with a clear vision of your console needs. 

     

    If you would like to discuss a project or require any additional information please do not hesitate to contact Darryl Lymer, Sales & Development Manager on telephone 07506 731 162, or at darryl@winsted.co.uk

     

    We look forward to hearing from you.

     

    Yours sincerely

     

     

     

     

    Stella Lewis

    Marketing & Development

  6. 0
    Wynand Jonker ·

    First need to summarize your

    First need to summarize your bill of quantity for example , Circuit breakers etc to Distribution Board.Isolators ,Cables ,Cable Racks , Transformers , UPS, UPS DB Boards Etc. Now do the same for Instrumentation. On your Project file start with

    Egg:

    Utilities:

    Cable Rack

    Trunking

    Power Equipment:

    UPS

    Generator

    Field Equipment":

    DB Boards

    Isolators

    Welding Plugs

    Lightning and small power:

    Plugs

    Lights

    Cables:

    Small Power

    LV Power

     

    This is a very quick guide line

     

     

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?