UPDATING A SCHEDULE

AB TimoMember for 15 years 3 months
Created
9
3
0

HI Gentlemen,

I have been updating the progress in primavers version 6, by using Duration as % complete type.But i have also heard that one should use Physical as % complete type...I then used physical but the results were the same.Can someone tell me that what is the difference in using these two?????

 

Regards,

9 replies

Oldest first
  1. 0
    Rob Llewellyn ·

    Hi Faiz Updating the progress

    Hi Faiz

    Updating the progress as a % of duration will only produce an automatic calculation of how long you have left to go, not the actual quantity left to achieve.  So far example if you have a 10 day activity which is worth 1000 man hours and you tell it you are 50% complete, Primavera (on those settings) will automatically presume you have 5 days of work remaining. In reality you may be 50% of the way through your original duration, achieved 60% of the workscope but there may be external factors which mean that the remaining 40% will now take 7 days instead of 5. 

    On projects i have always used % complete in relation to the quantity of achieved manhours and then input the remaining duration rather than letting it calculate automatically.

    I hope this makes sense!

  2. 0
    AB Timo ·

    Rob Llewellyn,Thanks for your

    Rob Llewellyn,

    Thanks for your reply.Now I have doubt in my upating process :(..

    I perform Following Steps,

    1.General tab--Percent type--Physical

    2.Status tab--activity Start Date entry---Percent Complete till Date (say 20%)

    3.Schedule at data date.

     

    is it correct Sir ?????

  3. 0
    Henry Chiu ·

    Hi Everyone, I am a new

    Hi Everyone,

     

    I am a new member to this planning site. I have a query about updating the baseline in p6. how can keep the backup. Normally in P3 you will save as another file. How about P6. Please advise.

  4. 0
    Mike Testro ·

    Hi Henry Welcome to Planning

    Hi Henry

    Welcome to Planning Planet

    You will get a better response if you start a new thread for your query in either P6 or P3.

    Also you only need to click the Save button once.

    Best regards

    Mike Testro

  5. 0
    Jorge Taguinod ·

    Let's say you have a 10-day

    Let's say you have a 10-day activity and you are using Duration %.
    At the 5th day, your Physical % is 40%.
    Dur % = 50 and Phy % = 40%

    No work is done on the activity for the next 5 days (ie no progress.  Physical % is still 40%.)

    Time lapsed is 10 days now.  Remaining Dur is still 5 days. At this point...
    Dur % = Actual Duration/At Completion Dur =10/15 days = 67%!  
    Without doing anything, your Dur % increased from 50% to 67%!!!

    In this picture, it shows that Physical % more acurately reflects reality.

  6. 0
    Manalao Salacop ·

    hi mike,hop u could help me

    hi mike,

    hop u could help me on my unexpected probs with my P6.1 stand alone primavera. When I was about to update my schedule, with the following facts: cost loaded, baseline - project, %complete type: duaration % complete.. Probs: when i update my schedule, 100% complete activities will have 100% earned value as well, but for the activities with below 100% complete will not give any value for the earned value at all nor even in performance % complete.

    THANKS

  7. 0
    Mike Testro ·

    Hi Manalo I don't use P6 so

    Hi Manalo

    I don't use P6 so sorry but I can't help.

    Best regards

    Mike Testro

  8. 0
    Manalao Salacop ·

    halu everyone,could anyone

    halu everyone,

    could anyone help me finding my solution in my P6 stand alone problem. when updating my schedule, with the following facts: percent complete type: duration percent complete, cost loaded, base line project.. problem, when updating, activities with 100% completed will give a 100% earned value, but for activities with below 100% completed or not finished activity will not give any earned value at all. thanks and god bless..

  9. 0
    Mohd Syahrul ·

    Duration %

    Duration % Complete Theoritically said u hv activity A1000 which is scheduled for 4days, then u update the schedule in 2nd days, the % should be 50%. Physical % Complete You have to enter the value in status tab manually, either based on your personal judgement or activity weights/steps.