Productivity

Arun VasanthMember for 17 years
Created
3
2
0

Dear Friends

Letme know the productivity of Secant pile ..

Mike Iam  asking a rough idea.

regards

Arun

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Arun It all depends on: 1.

    Hi Arun

    It all depends on:

    1. Size and depth of the pile

    2: Type of rig ie Continuous Flight Auger

    3: Number of rigs

    First you have to drive the "Soft Pile" then the reinforced pile so you need two operations.

    Do not forget the ring beam and then the temporary supports during excavation.

    Ask your potential piling operator for precise details.

    Best regards

    Mike Testro

  2. 0
    Arun Vasanth ·

    Thankyou mike But please give

    Thankyou mike

    But please give me a rough idea for soft soil with 1 m dia 20 m depth..

    Please

     

    Regards

    Arun

  3. 0
    Arun Vasanth ·

    Mike Please help to

     

     

    Mike

    Please help to resolve this issue