Project management

Arun Kumar SinghMember for 15 years
Created
6
2
0

What the difference b/w project baseline, primary, secondry & tertiary baseline programme ?

6 replies

Oldest first
  1. 0
    Roland Payawan ·

    PORJECT BASELINE i may say is

    PORJECT BASELINE i may say is the first contractual approved master programme. Primary Baseline basically the Project Baseline or the approved revised programme. Secondary and Tertially baseline for me is the previous reporting period programme, that I used to  for easy monitoring which activities missed its previous reporting period target start and completion date.

  2. 0
    Gary Whitehead ·

    The project-level baseline is

    The project-level baseline is used for project/activity usage spreadsheets and profiles, as well as dates and earned value calculations 

    The primary, secondary and tertiary are just for earned value and dates

  3. 0
    Deff Usman ·

    It is the reference of your

    It is the reference of your contract schedule,,,Thats you called the baseline schedule.

  4. 0
    Arun Kumar Singh ·

    HOw many activity we can use

    HOw many activity we can use in a single project and what's the no of relationshipe we can assign in same programme.

    means i have one programme in that 20000 nos activity with arround 60000 relationship

    i want to know max no of activity and relationship in a single programme ??

  5. 0
    Mike Testro ·

    Hi Arun The simple answer is

    Hi Arun

    The simple answer is how big is your software database?

    Best regards

    Mike Testro

  6. 0
    Deff Usman ·

    The Project baseline is your

    The Project baseline is your original reference for the project,Secondary will be the next reference and so on....