Schedule transition in different stage
- Created
- 5
- 2
Hi all Planners,
In my company, we have regular process of scheduling.(FEL1/2/3,schedule implementation,facility operation..)
It means project team and me need to initial schedule at the early schedule before we issue PO to vendor or subcontractor.
So, Schedule will base on the previous project experience to develop.
Here is my question.
We will receive the subcontractor schedule after we issue PO.But working sequence and weighting of WBS are different from ours which consult with our construction engineer.(But the milestone date still follow our request)
It will show a big difference in progress between subcontractor and us.
Because subcontractor use cost to be the base of their weighting but our construction engineer base on his experience.
Different WBS with different base. Project team doubt the gap of progress which provide by subcontractor and me.
Will you replace your construction schedule(which make in the early stage) with subcontractor's schedule?
To align you progress in construction portion with subcontractor.
Or what is the right way to proceed this practice.
Thanks!
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?