What does the following mean when doing schedule analysis
In the Open Standard
Raul SantosMember for 16 years 11 months
- Created
- 3
- 3
0
What does it mean when you run a Varance Report (comparing end dates between the baseline schedule against the current schedule) and you have negative variance for some activities and also TF = 0 for those same activities? These activities have slipped to the right (delayed), but still meet the schedule end date. How can this happen? Can you please explain what might be happening? Thanks in advance for your responses.