Schedule submission
- Created
- 2
- 2
TFIF everyone! :-)
Quick one for those of you with both hats on.......
For those of you working for a 'client' do you insist / stipulate that the contractor submit the schedule source files, be it .xer, mpp etc.. at the reporting period?
Is this puerely down to the type of contract involved, or is this a requirement? Wouldnt one assume that if a contractor is refusing to submit their .xer then maybe they have something to hide, and their pdf's are doing just that? We are on an NEC option A, and it doesnt appear to mention what 'should' be submitted.
For those of you on a contractor side, what formats do you submit? what do you do if a client insists you send the source files?
I'm on the client side ( boo hiss lol) and don't know whether to demand the .xer so I can interrogate their schedule as the pdf's they submit are utter crap and dont tell me much at all.
Any feedback greatly appreciated.
Walshy
2 replies
Oldest firstLog in or join to reply