You shall decide based on your own needs what each level means, the same goes for your clients. Different job types might require more or less levels, depending on a single all inclusive generic level definition might be too restrictive, and this applies for your different Portfolios.
It is pretentious and wrong for others to force you to exclusively use their definition because theirs is better than yours as if the exclusive owners of all truth.
I keep a WBS based on Area at a higher level and Function at a lower level, a WBS based on Function at a higher level and Area at a lower level, at rare times I keep an additional based on responsibility and of course, another for whatever the Client asks.
More frequently I define my WBS by a more free structure known in some software as Outline Structure to differentiate from their more restrictive WBS structure which is similar to organizing by activity codes where all activities are located at the same level.

What if your Global Portfolio which include other jobs by other clients/owners each based on different WBS none of which is compatible with the caprices of a particular client/owner?
The solution is simple, maintain your jobs as per your own company standards and create a WBS for this purposes, then create additional WBS dictionaries for the needs of your clients. If your software do not provide for multiple WBS I suggest you dump the “trompo toy” and get serious software.
Regards,
Rafael