Extract and Include
- Created
- 1
- 4
Hello friends,
Previously i prepared a schedule for a Project,
Schedule 1: includes WBS A - WBS B - WBS C (all WBS & Activities are inter related)
Later due to change in project i removed WBS C totally. And even made changes in relationship between WBS A & B activities.
Schedule 2: includes WBS A - WBS B.
Now i have been asked to include WBS C.
My question is whether can i extract WBS C from Schedule 1 along with the relationships that C activities had with A & B and whether can i include/attach WBS C in Schedule 2?
Experts please guide me. Hope u understand my problem.
Regards,
Sivaganesh.S