Skip to content

how items are included in a master schedule

Sharjeel FaizMember for 11 years 6 months
Created
3
3
0

If the scope of an EPC project consists of 100 items, big and small, how does the planner include it in the master schedule?

thanks

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Sharjeel,Depending on how

    Hi Sharjeel,

    Depending on how the master schedule is setup and what is the company policy and procedures for Master Schedule.

    Some company procedure requiring Level 3 for integrated Master Schedule and Level 4 & Level 5 for contractors schedule.

    You can code the contractor's level 4 or level 5 to match Master Level 3 schedule for easy update.

  2. 0
    Zoltan Palffy ·

    on option is to make samller

    on option is to make samller schedules and then when importing select the master schedule and during the importing process select add to existing project instead of creat a new project.

  3. 0
    Rafael Davila ·

    Might also be of interest the

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?