Loading Schedule with Maanhours

Sm PumMember for 14 years 11 months
Created
6
1
0

HEllo

For our client we need schdules uploaded with manhours (Not Decipline wise).I am confused that when we talk about manhours for aa certain activity then does it means that the this value of manhours is for each decipline or it is collective.For Example
In Blinding concrete=6 Mhr/Cu.m
Does it mean 6 Mhs for Concrete Mixer,6 for mason,6 for mason helper,6 for carpenter etc....or

it is sum of manhours for each decipline?

In above example I will say that each resource will work 6 hours to pour 1 Cu.m of blinding concrete??Is it correct statement?

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Concrete Mixer operator = 1

    Concrete Mixer operator = 1 hr

    mason = 2 hrs

    mason helper = 2hrs

    carpenter = 1 hr

     

    The sum of hrs they work = 6 man hrs

    means 6 man hours for 1 cu m of blinding is the productivity rate.

  2. 0
    Vladimir Liberzon ·

    I wouldn't call it

    I wouldn't call it productivity rate.

    The work will not be accelerated if we will add helpers to this crew.

  3. 0
    Raymund de Laza ·

    Vlad, I understand your point

    Vlad,

    I understand your point and the illustration you see was just an EXAMPLE of how to define the term "MAN HOUR" in the productivity.

     

  4. 0
    Clint Marquez ·

    @SM - You need also to

    @SM - You need also to visualize the quantities of each activities.

    Like on your example,


    1cu.m of blinding concrete (qty) = 6mhr/cu (prod.rate)


    > Actually, 1-cu.m of concrete can be done in less than an hour, especially if the area to be poured is quitely open and spacious.
    > @ 6mhrs/cu. m- you can do assigning 6-workers for just an hour of work to complete this activity.

     

    Thanks. 

  5. 0
    Clint Marquez ·

    @SM - You need also to

    @SM - You need also to visualize the quantities of each activities.

    Like on your example,


    1cu.m of blinding concrete (qty) = 6mhr/cu (prod.rate)


    > Actually, 1-cu.m of concrete can be done in less than an hour, especially if the area to be poured is quitely open and spacious.
    > @ 6mhrs/cu. m- you can do assigning 6-workers for just an hour of work to complete this activity.

     

    Thanks. 

  6. 0
    Ahmet Tuter ·

    I would definitely say that 6

    I would definitely say that 6 mh means the total of all of the manhours going into pouring the concrete.

Log in or join to reply