Cost Entering in Schedule

Ashik GBMember for 15 years 10 months
Created
1
5
0

Hello Everybody,

I have only BOQ & Mile Stones and we have not seggregated the Cost into seperate resources.

Now i want to enter the cost as per the mile stones for Tracking Purpose.

So, Can anybody help in this regard like assisgning only BOQ rates for the activities or need to enter the individual resources?

Regards,

Ashik

1 reply

Oldest first
  1. 0
    Rafael Davila ·

    Not all software require to

    Not all software require to use resources to assign costs, some allow to assign costs directly to activities as well as to resources. In case your software only allows for costs to be assigned via resources then I suggest using a resource named BOQ Costs, a resource defined not to be leveled, and then use it to assign costs to activities while using cost codes to match BOQ codes and cost centers for detailed distribution and reports.

    Please disclose what software you use in order to get a specific answer. I suspect it might be P3, SureTralk, MSP or Asta PP because of your question about the requirement for resources being required to assign costs. And while MSP is the best selling schediling software in the world we do not know if it is the software you are using.