Skip to content

Interview Question for the Planning Engineer

Nouman ZiaMember for 13 years 3 months
Created
5
3
0

Hi guys,

Given below are list of interview questions faced by Planning Engineer , other than their personal and Experience. if anyone like to add more u are welcome pls .............

I would appericiate if some has brief answer of the questions listed below.

 

Q-3: What are the three basic PROCESSES for preparing the baseline program?

Q-4: You have just received the baseline program form your contractor what are the few major things you will check immediately?

Q-5: What are the components of Baseline program?

Q-6: How you will load the resources & Cost in your baseline program using P3 & P6?

Q-7: What is an S-Curve? And how many types are there?

Q-8: Why we use Curves instead of bar charts?

Q-9: What is the difference between Bar chart & Schedule?

Q-10: What is the difference between schedule & baseline?

Q-11: You have approved the baseline program of a contractor now what will be the next step?

Q-12: what is the difference between Duration% Compo and Physical % Comp.?

Q-13: What is the difference between physical % and % weight age? And what is the difference between weighted % and Un-Weighted %?

Q-14: what are three parameters for % weighted in any project?

Q-15: Being a contractor what is the most important parameter for % weight age? And as a consultant which parameter of % weighted you will use for progress monitoring?

Q-16: How you will breakdown the % weighted of a building project from start to finish?

Q-17: The contract has submitted the claim for EDT how you will analyze this claim? Define the steps for claim analysis?

Q-18: Your program is showing a delay in progress for more than specified time what will you do in this case?

Q-19: What is the difference between TO COMPLETE & AT COMPLETION?

Q-20: What is the difference between Milestone and Flags?

Q-21: What is the difference between Estimate & Budget?

Q-22: What is the difference between recovery program & revised program?

Q-23 what is the difference between Target & Forecast?

Q-24: Draw an S-Curve Showing the Baseline program, Updated Progress, Recovery in progress?

Q-25: How you will present the planned % Complete along with the Actual % Complete in the summary bar of the updated program?

Q-26: How you will show the overall summary of % cornp. at each WBS level?

Q-27: Which planning Software you will be more comfortable with and why?

Q-28: What is the Long Lead Items? And how you will define then in your program?

Q-29: How you will recover the delay in your project?

Q-30: What do you mean by PS Items?

Q-31: What do you mean by PC rate items?

Q-32: what are Thresholds?

Q-33: What is Fragnet?

Q-34: How you will monitor the critical path?

Q-35: Up to which level you will breakdown your activities in your baseline program and in your updated program (for monitoring only)?

Q-36: What is Variance Analysis?

Q-37: What is the difference between controlled milestone & Key Milestone?

Q-38: What do you mean by Concurrent Delays & Critical delays?

Q-39: Have you ever worked with different formats for progress monitoring? And what are those?

Q-40: Your program is showing a delay and you were asked by your manager to print for him a report for the delayed items how you will make it in a quick time?

Q-41: What is the difference between EV & AC?

Q-42: How you will make the Two Weeks Look Ahead from your updated program?

Q-43: What is the typical WBS for a building project?

Q-44: What are the two major types of calendars you will use in your baseline program?
Q-4S: What is a Risk?

Q-46: How you will make the Risk Register?

Q-47: What is the difference between Mitigation & Acceleration?

Q-48: What is the major role of planning engineer in the Project management?
Q-49: What is the difference between Cost & Revenue?

Q-50: How you will define the learning curve? (Give example) 

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi NoumonWhere you setting

    Hi Noumon

    Where you setting them or answering them?

    Best regards

    Mike Testro

  2. 0
    Nouman Zia ·

    Hi , I need breif awnsers to

    Hi , 

    I need breif awnsers to these questions.

    Thanks

  3. 0
    Mike Testro ·

    Hi NoumonSo you want someone

    Hi Noumon

    So you want someone to answer your interview questions for you.

    I doubt that you will get any response - except maybe Q27 which should always be Asta Powerproject.

    Best regards

    Mike Testro

  4. 0
    Viktor Pletnyov ·

    And now the contest for the

    And now the contest for the best answers!
     
    Who will start?!
  5. 0
    Nouman Zia ·

    Q-22: What is the difference

    Q-22: What is the difference between recovery program & revised program?

    Recovery Program:  This program is to bring a late running project back to the schedule without zero cost to the client.

    Revised Program:This the program as result of any variation or change proposed by the client.

    Accelerated Program:  This is the program to bring the project finish date earlier at the cost to the client.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?