Dear All;

I am involed in defining a project budget. Costs for Direct manpower, Mahinery, materials, cost & overheads at site have been calculated. No I need to add indirect cost to complete my activity estimates process. And also at later stage I shall need to update the indirect cost alongwith direct cost. We have cost accounts but I am not sure how to distribute indirect cost on different projects.

 

Regards

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Process is not

    Process is not hard:

    -understand the various indirect costs that will apply

    -estimate the costs per time period of each of these costs

    -estimate when and for how long these costs will be incurred

    -Load them onto activities

     

    eg:

    project planner, £300 per day (full time), required full time for 1st month, 50% from then until end of construction.

    or:

    Procurement manager, £40 ph, 8 hr/day, required 1 day/week from commencement of tender evals, full time from commencement of tender negotaitions, down to 1 day/week once all orders are placed, zero after final delivery.

     

    Typically indirect costs are loaded onto LOE / hammock type activities

     

    Is there anything specific you are not sure about?

  2. 0
    AB Timo ·

    Thanks Gary;Suppose We have a

    Thanks Gary;

    Suppose We have a Planning Department. Account Code 0001. Now this Department will be responsible planning & monitoring of 10 Projects. Now while making Budget should I distribute the cost as lumsum using hammock?

    Secondly during updating , is it better idea to "check" the "Auto compute actuals" box in resources so that this indirect costs fill automatically with time?