Baseline Schedule made up of several projects linked together

Rami Al HaddadMember for 21 years 4 months
Created
1
3
0

Ladies and Gents,

 

Just wondering what are the contractual implications of producing a baseline schedule (in P6) that is made up of several projects which are linked together (through external relationships from project to another)! 

Thank you,

Rami

1 reply

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Rami As far as I know P6

    Hi Rami

    As far as I know P6 does a BL project by project. So you'll assign to each project. If you open all of them all BL information is given as well.

    I hope I understood your question correctly.

    Regards

    Dieter