Skip to content

Bidding Schedule for EPC

Wally Boy CasugaMember for 13 years 3 months
Created
2
2
0

Dear all,

Good day! I was asked to draft a bidding schedule for Engineering and Procurement as well as construction management for an H2 project. Can somebody extend their helping hands?

Thanks,

Wally

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Wally - welcome to

    Hi Wally - welcome to planning planet - next time only hit the "save" button once.

    The basic principle of a bid tender is to see if the work can be completed in the stated contract period.

    Do not try to squeeze durations to make it fit - that is for the bid manager to decide after he has all the facts.

    So make sure your durations and logic is correct - particularly with the Engineering / Procurement sections.

    Work at level 4 with FS links.

    Make sure that the Employer's deliverables are set with clear milestones linked ALAP to the Contractor's task.

    Best regards

    Mike Testro

  2. 0
    Wally Boy Casuga ·

    Hi Mike, Thanks. Been trying

    Hi Mike, Thanks. Been trying to delete the 2 posts but cannot find the option. I've been given the duration already for the aforementioned tasks. What I'm after are the processes/activities involved in EPC bidding. Do you have sample schedule either in p6 or MS project that I can refer?

    If in case, can you kindly email at this id? wally.casuga@gmail.com

    Regards,

    Wally

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?