Skip to content

Subcontractor's Schedule Imported but no Actual Earnings

Brandon WallMember for 11 years 11 months
Created
4
4
0

Hello,

I have received and imported an update from a subcontractor which has actual progress for activities.  My problem is that their actual material and labor resources are all zero's.  We have both shared screen shots and in his schedule he has values for the actual material and labor.  I do not have any of those actual resource values that he is showing me.  I know that he is sending me the correct file and my resourece settings are as follows.

Labor Resource

Details = Auto Compute Actuals is checked.  Calculate costs from Units is checked.

Units & Prices = Price / Unit = $0.00

Material Resource

Details = Auto Compute Actuals is checked.  Calculate costs from Units is checked.

Units & Prices = Price / Unit = $1.00

My instinct tells me that the problem was in my Price / Unit.  I thought that my Price / Unit would have to match his Price / Unit but I have changed these values and nothing changes after scheduling.  My understanding is that he should have all values entered accordingly and send me the file.  After importing I SHOULD be seeing the same actual dollars and hours that he has regardless of the Price / Unit settings.

Any help is very much appreciated.  I have not seen this problem before.

Thanks,

Brandon

 

 

 

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Brandon, During import go to

    Brandon, During import go to options of importing new resources instead of update existing which was set as default. regards..
  2. 0
    Raymund de Laza ·

    Brandon, During import go to

    Brandon, During import go to options of importing new resources instead of update existing which was set as default. regards..
  3. 0
    Brandon Wall ·

    Thanks for the help Raymond.

    Thanks for the help Raymond.  That was an easy fix and lesson learned.

  4. 0
    Raymund de Laza ·

    You are Welcome Brandon.

    You are Welcome Brandon.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?