Store period performance

Janaka SamarathungaMember for 11 years 11 months
Created
3
2
0

Dear Experts ,

When I checked our contractor's weekly and Monthly report , I found that each weekly and monthly period showing diffrent actual figures for the same month . I guess promavera just distribute the actuals over the period every time when it gets updated

My first question is - is this an reasonable reson to say that  data comes from P6 software ? or we have to do it manually to make sence ?

Second- Contrator is reluctant to use the option "Store period performance"  

your view please ?

Janaka

 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Using store period

    Using store period performance will put the actual cost into the correct time frames.

    why is the contractor reluctant to do this ?

  2. 0
    Zoltan Palffy ·

    Using store period

    Using store period performance will put the actual cost into the correct time frames.

    why is the contractor reluctant to do this ?

  3. 0
    Raymund de Laza ·

    Actual Cost That was Auto

    Actual Cost That was Auto Calculated by Primavera is a fancy Actual Cost. Actual Expenses is the Actual Cost supposed to be manually entered and it is supposed to be Saved periodically using the "Store Period performance".

     

    Regards,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?