Revised and Recovery Plan

Moutaz AldeibMember for 22 years 9 months
Created
3
2
0

Dear Planners,

Can any one tell me accurately what is the difference between "Revised Plan" and "Recovery Plan", and in which cases they are used?

Best,

Moutaz

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi MoutazYou prepare a

    Hi Moutaz

    You prepare a recovery plan to try to reduce a delay situation.

    You revise a plan if there is a different way of doing things.

    Best regards

    Mike Testro

  2. 0
    Ahmed KHR ·

    We revise a programme in case

    We revise a programme in case of EOT, scope change (addition or deletion), Quantities changes

    Recovery plan is the way to absorbe the delay and turn back to the original project finish date.

  3. 0
    Moutaz Aldeib ·

    Thanks Ahmed and

    Thanks Ahmed and Mike

    Best,

    Moutaz