Time schedule in tender phase

Haytham SaadMember for 13 years 6 months
Created
2
2
0
HI All
 
i'm currently working on a schedule for tender phase for a shopping mall my company is participating in, the problem that my managers are requesting detailed schedule and detailed activities and also asking if we could provide a resource loaded schedule , in my opinion the tender phase is all about the time frame for project and the key milestone and the sequence of work, here comes the question :D
 
what do you think the best practice for providing time schedule in tender phase ???
 
if any one can provide me a sample of his/her tender schedule as a guide that will be great.
Regards
Haytham saad

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi HaythamA tender programme

    Hi Haytham

    A tender programme should be a bottom up level 4 in as much detail as possible.

    Its purpose is to:

    1. Check if the construction period is feasible.

    2. Assist the estimator on plant and scaffolding durations

    3. Carry out what if scenarios

    This cannot be done in a level 3 programme.

    And it must be resource loaded so that the durations reflect the cost plan.

    A shopping mall is not a complex structure and a skilled and experienced planner should have a programme for first review in about 3 days.

    Best regards

    Mike Testro

  2. 0
    Haytham Saad ·

    Dear mikeThanks for ur reply,

    Dear mike

    Thanks for ur reply, the problem is that the scope of work is wide from civil:concrete-steel works & Electrical & Mechanical andit will be difficuilt  to reflect all the BOQ items as Activities in this phase , also i need to ask u waht other report should i present with my schhedule ??

    Thanks

Log in or join to reply