Skip to content

Updating schedule

John K. LMember for 11 years 4 months
Created
4
2
0

Hi guys,

I'm a construction management student and asked to do an assignment about "Updating Schedule", so what is meant by Updating Schdule in project management, and what is the purpose of updating schedule?

 

Regards

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    updating a schedule is when

    updating a schedule is when you apply progress to your schedule thru a certain date. An activity can be in one of three stages

    not started

    started (but not finished) = in progress

    or finished - completed 

    What you do is indicate any activities that have started recored the actual date they have started. If they are not finished you input the remaing duration for the activity to complete = in progress

    You also record any activities that were previously started and have now finished and you indicate the actual finish date.

    You also recored any activities that have started AND completed during the reporting period and indicate theri actual start and finish dates

    You would also add any new work or change order work that ws issued to you. 

    You then chnage the data date (PROGRESS THRU DATE) and recalculate the schedule.

    The purpose of this is show where you are on your project either being on schedule, ahead of schedule or behind schedule. 

  2. 0
    Patrick Weaver ·

    Zoltan's comments below are

    Zoltan's comments below are structurally correct, but there is more to updating than simply processing information.  This paper from 2002 is still current: Managing for success - the power of regular updates: http://www.mosaicprojects.com.au/PDF_Papers/P002_MFS_Full.pdf 

    For more on the overall process of developing and maintaing a 'good schedule' see: http://www.mosaicprojects.com.au/PDF/Good_Scheduling_Practice.pdf 

  3. 0
    Rafael Davila ·

    For cost loaded schedules

    For cost loaded schedules please take a look at the following reference.

    http://www.nflaace.org/index_files/john_orr_cost_loaded_schedule_updating_pdf.pdf

  4. 0
    Zoltan Palffy ·

    While Patrick's references

    While Patrick's references may be helpful the links do not work. I have stated the basic concept.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?