Load Labor Units/ Manpower in an Updated Schedule

Deepak KhundrakpamMember for 15 years 11 months
Created
3
1
0

Dear Friends,

My Client is asking to load resources ( Manpower ) in the existing Primavera Schedule (P6)  which is already updated . I have never came across such situaion  and am not sure , technically can it happen. Can ayone shed some light on this.

Thanks,

Deepak

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    yes you can do it add a

    yes you can do it add a resource in the resource dictionary 

    then add a resource to each activity and put in the budgeted units (manhours for each activity)

    then just update your remaining manhours for activities that are in progress 

  2. 0
    Deepak Khundrakpam ·

    Thanks for your valuable

    Thanks for your valuable response!! But do we need to load the Manpower in all the activities including the completed ones. and what about the ongoing activities ?? we shall put only the remaining units or total units is also required to show a realistic Manpower Histogram !!

    Thanks in advance!!

  3. 0
    Zoltan Palffy ·

    my answer reains that

    my answer reains that same 

    add a resource to each activity and put in the budgeted units (manhours for each activity)

    then just update your remaining manhours for activities that are in progress 

    for your activiites that are completed update the reamining units as zero