New Tasks With '0' Float Throughout the Schedule

Reggie WinfreyMember for 11 years
Created
1
3
0

I am trying to create a test schedule in MS Project 2010.  The problem is that with every new task that I create, there is no float associated with the tasks being entered.  I have tried the following:

1. Moved the Project Start date out six months or more

2. Ensured all of the tasks were linked

3. Added a Deadline Date for the last tasks in the Network

4. Changed all Constraint Types to ASAP

No matter what I have done, there has been minimum to no float in this test schedule.  Can someone tell me what I"m missing on this?

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi ReggieIf you have a

    Hi Reggie

    If you have a continuous cascade of FS links then tasks will alaways be critical.

    Best regards

    Mike Testro