External Links in p6 Schedule need removing - inter project links

Mark GriffinMember for 20 years 4 months
Created
2
3
0

So i have opened my schedule today in p6 and relised someone else has copy parts of my project into their's as they needed the same type of activities in there schedule.

 

However when they have copied and pasted the WBS it they seem to have had the Only between copied activiies un checked (in the copy activity options) and thus i now have hundreds of inter project links as it is maintaining those links from my schedule.

 

How can i quickly removed these as there are hundreds

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you have several

    you have several options

    Option 1  go to tools schedule 

    select options

    then select ignore relationships to and from other projects

    option #2

    filter for all activities

    right click columns 

    expand the dates availability on the left and choose

    External Early Start and also choose External Early Finish

    now in the External Early Start column Blank out the dated 

    now do a fill down a

    Now do the same thing for the External Early Finish Column

    Option #3

    go to tools

    global change

    New (on the right)

    Where  (leave this line blank)

    then

    External Early Start = (leave the rest of the line blank)

    and

    External Early Finish = (leave the rest of the line blank)

    then on the right select change

    then commit changes

     

    what ever option that you choose make sure to run the schedule calculations after you run your option

  2. 0
    Mark Griffin ·

    Thanks for the post back. I

    Thanks for the post back.

     

    I have check both the late and early exertnal finishs but the coloumns are blank.

    The scheduling options is not ticked but i dont beleive the schedule will be affected by these links.

     

    from what i understand my collegue has copied the WBS so all my activities have successor to their project but that is it, so they are all open ends.  It is just very confusing going to the successor box and seeing 15 links in that are of no use.

     

    i can go through and delete but i have 2500 activities in my schedule to check.