How can i sheft the quantities of budgeted labor unit into the column of default units/time?
In the Open Standard
Moustafa HusseinMember for 9 years 6 months
- Created
- 3
- 4
0
Hello planners,
I am facing a problem in the project baseline. I received a baseline of 5,000 activities, where the resources are loaded wrong. The old planner placed the default units/time quantities in the column of budgeted labor units my mistake. Can someone guide me or help me in shifting them from the column of budgeted labor units to default units/time?
I tried to copy the program, and maintain it then assigning it. But when i go to the global changes, there is no column named as BL1 budgeted labor units.
Help me please.
3 replies