Store Period Performance - Calendar Months
In the Open Standard
Martin KerrMember for 9 years 5 months
- Created
- 1
- 2
0
I have a new client who have just invested in P6 for the first time (R16.2)
I am in the preocess of setting up to record earned value. Not currently looking to record actuals in P6.
The clients reporting calendar is aligned to calendar months.
Do I have to set up reporting periods aligned to calendar months manually in order to store period performance or is there a quick way to do this?
'Batch Create Financial Periods' doesnt appear to have options for calendar months.
Thanks
Martin