Step By Step Procedure for Recovery Schedule - Reg

Umashankar VijayanMember for 14 years 1 month
Created
1
3
0

Dear All,

This is Umashankar Presenting greetings of the season!

I am currently involved in producing a revised schedule.  The Project has a contract duration of 3 years; of which 1 1/2 years is already elapsed.  The client issued a Variation Order for descope and the Contract Completion date still remains the same.  

With this scenario, I am forced to produce a revised schedule on the date of VO issued.  The revised programme shall be produced in a different execution strategy as that of baseline programme due to change in Traffic Diversion Scheme post approval of Baseline Programme.

Hence I have to make the schedule to reflect the actuals until VO issue date, i.e., 

For Completed Activities:

Original Duration = Actual Duration

Planned Start and Finish Dates = Actual Start and Finish Dates

For in Progress Activities:

Original Duration = Actual Duration + Remaining Duration

Planned Start = Actual Start

Planned Finish = Finish

Until this step everything went well; but there was no effect to the earned values, i.e. Planned Value cost and Earned Value cost doest not match.

 

Can anyone suggest how to make the Budgetted Cost, Planned Value Cost and Earned Value Cost equal before doing any changes to the Programme?

 

Thanks in Advance,

V. Umashankar.

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    run a global change to make

    run a global change to make them equal 

Log in or join to reply