Skip to content

Concurrent Delays in the Schedule

Dimple DeanMember for 11 years
Created
2
5
0
Hi All,
 
Just asking on this situation regarding concurrency.
Contractor's Delay from 30 Oct 2016 to 30 April 2017.
Client's Delay from 30 Jun 2016 to 30 Mar 2017.
Is it a concurrent delay?
 
many thanks!

2 replies

Oldest first
  1. 0
    Jithin Kambhikanam ·

    Hi Dimple,Ya it is Concurrent

    Hi Dimple,

    Ya it is Concurrent delay.

     

    So you can apply LD for a Duration of Contractor Finish Date - Client Delay Impact Date = 30 April 17 - 30 Mar 17 = 30 Days.

     

    Mike would be able to answer it much better.

     

    Regards

    Jithin

  2. 0
    Zoltan Palffy ·

    Contractor's Delay from 30

    Contractor's Delay from 30 Oct 2016 to 30 April 2017

    Client's Delay from 30 Jun 2016 to 30 Mar 2017.

    Is it a concurrent delay?

    if you hand draw this on paper it will be crystal clear
     
     There are 2 parts attributal to the contractor delays. The Contractor Delay #1 is from June 30, 2016 to October 29,2016. The concurrent portion of the delay is from October 30, 2016 to March 30, 2017. The Contractor Delay #2 is from April 1, 2017 to April 30, 2017

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?