schedule % complete

Anil M GMember for 9 years 2 months
Created
1
2
0

Hi ,

I have some issues,

I need to use Expense Cost and Man-hour related progress. I want to see the Planned progress and Actual progress based on the Expense Cost and Man-hour same time.

I believe we can load Expense Cost as well as Man-hours to the Schedule.

Now the issue how to get Schedule %? How to get Schedule% based on Expense Cost and based on Man-hours separately.

Is it possible?, How it can be switched in P6?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    view show on bottom resource

    view show on bottom resource useage profile 