Skip to content

Cost Loading a Schedule - Input From ?

Jithin KambhikanamMember for 15 years 6 months
Created
7
2
0

Hello Everyone,

Just understand where the Cost of each activity would come from if you have to Cost Load a schedule.

The BOQ of a Project would have a lumpsum quantity say for example,

Concrete = 250 Cu M X 350$ / Cu M = 87,500 $.

And in schedule we have activity say,

  • Concrete - Slab on Grade
  • Concrete - Column Ground Floor
  • Concrete - First Floor
  • Concrete - Column First Foor
  • Concrete - Second Floor. 

So how can a Planning Engineer allocate the Cost for each activity based on quantity. 

Regards

Jithin

7 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    create a resource make the

    create a resource make the name concrete make the type a material resource 

    then in the units & prices tab put in your price if c Cu M of concrete $350

    now go to the concrete activites in the schedule and in the resource tab assign the concrete resource

    now iin the budgeted units put in the Cu M of concrete for this activity 250 

    it will take the budgeted quantity (250) and multiply by the price per unit ($350) and give you a budgeted cost of $87,500

  2. 0
    Jithin Kambhikanam ·

    Hi Zoltan,That I do know but

    Hi Zoltan,

    That I do know but there would be many activities related to Concrete in the schedule like I have refered.

    I would like to know how to split that Overall Quantity to per Activity Quantitiy so that we can allocate cost to each activity.

    Who can give that Input.

     

    Regards

    Jithin

  3. 0
    Zoltan Palffy ·

    filter for your concrete

    filter for your concrete activities 

    select edit then select all 

    right click and select assign tnen select resources

    then select the concrete resource that you make for concrete material 

  4. 0
    Jithin Kambhikanam ·

    Hi Zoltan,but who will give

    Hi Zoltan,

    but who will give the Quantity for each activity of Cocnrete. Which engineer or department would give me the quantity so that I can allocate the quantity to those activity. Say there are 

     

    Activity IDActivityBudgeted QuantityUnit Rate
    A1000Slab on Grade?250
    A1010Column - First Floor?250
    A1020First Floor?250
    A1030Column - First Floor?250
    A1040Second Floor?250

    So who would give me the budgeted quantity / Activity.

     

    Regards

    Jithin

  5. 0
    Zoltan Palffy ·

    who made the schedule

    who made the schedule typically you have to know how much (units or quantity) before you can say how long (duration)

    for example you cant just say it will take me 5 days to install lights in a particular room withput 1st knowing how MANY lights (units or quantity) are in the room and what type of lights there are. From there you cknow your rate of installation for 1 man or a crew and then you decide on how many men or crews to use. This will deteremine your duration. How much before how long. 

    some one should have the initial quantity take off who bid it  ?

  6. 0
    Jithin Kambhikanam ·

    Hi Zoltan, So you need to

    Hi Zoltan,

     

    So you need to Contact the tendering team to get the detail of the Quantity to cost load the schedule initially. The tendering team would have the detail of how they came up with the overall quantity.

    So the Input would be from Tendering Estimation Team.

    Regards

    Jithin

  7. 0
    Zoltan Palffy ·

    that can be one source but

    that can be one source but usually after the project is awarded the field team actually doing the work will take the project off again to ensure that nothing has been missed and to verify the quantities from bid. 

     

    so now you have to places to get the quantities. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?