After receiving drawings and BOQ's from client what would be the the next procedure toward project execution of Piping project.?

14 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    pricing ?

    pricing ?

  2. 0
    Zoltan Palffy ·

    creating a schedule to see

    creating a schedule to see how long the project will take to do

  3. 0
    Muhammad Ahmad ·

    Sorry I wanted to know about

    Sorry I wanted to know about planning and scheduling of piping project. Means wbs, activities !
  4. 0
    Muhammad Ahmad ·

    ,

    ,
  5. 0
    Zoltan Palffy ·

    1. create a wbs2. create

    1. create a wbs

    2. create activities and assign activities to a wbs

    3. assign relationships to activities

    4. assign durations to activities

    5. calculate the schedule 

    6. assign resources manhours and costs

    7. Create a baseline schedule narrative

    8. issue for review

    9. incorporate comments from review

    10.. Issue final version

  6. 0
    Vladimir Liberzon ·

    Zoltan,I suggest some changes

    Zoltan,

    I suggest some changes to the order that you proposed:

    1. create a wbs

    2. create activities and milestones and assign activities to a wbs

    3. assign relationships to activities

    4. assign resources to activities

    5. calculate and assign durations to activities

    6. assign costs to resources and activities

    7. set schedule constraints

    8. calculate the schedule and the budget

    9. create a baseline schedule narrative

    10. issue for review

    11. incorporate comments from review

    12. Issue final version

  7. 0
    Muhammad Ahmad ·

    Thank you brother. I am new

    Thank you brother. I am new in this field. Can you plz tell me exact wbs for simple piping means mobilization, shop fab, field fab and also the activity details, this is my email Ahmad96197@gmail.com if you can send me the. .Xer file, it would be great.
  8. 0
    Zoltan Palffy ·

    wbs would be how you want to

    wbs would be how you want to break your piping down into smaller pieces like

    You could have 

    General and in that wbst mobilization

    Submittals?Approvals list your submittals and approvals here 

    Procurement list the items that you are procuring 

    Then you can break you work down as per this devel of detail

    Building

    ........Level

    ............Area

    ...............Zone

    ..................And any other level to here the actual piping is being installed maybe by system or large bore vs small bore

     

    no xer

  9. 0
    Muhammad Ahmad ·

    Thanks brother. If the

    Thanks brother. If the piping material is provided by the client and contractror have to fabricate it and then erection what kind of wbs will be in this conditions means sample or federal wbs for piping?
  10. 0
    Johannes Vandenberg ·

    Hi MuhammadTry this Regards

    Hi Muhammad

    Try this

    Simple, Free Image and File Hosting at MediaFire

     

    Regards Johannes

  11. 0
    Muhammad Ahmad ·

    Thanks if you can plz attach

    Thanks if you can plz attach the erection pre commissioning and activities also.
  12. 0
    Raymund de Laza ·

    Hello Muhammad,If you would

    Hello Muhammad,

    If you would mind, send the BOQ and Drawings and I prepare your detailed Schedule ready for Submission.

     

    Regards,

  13. 0
    Muhammad Ahmad ·

    Plz provide your email

    Plz provide your email address, I will email all details to you.
  14. 0
    Raymund de Laza ·

    Please open your Private

    Please open your Private Message.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?