A few random thoughts:
1. Nothing will happen quicker just because you reduce the duration of a schedule activity. Look at how long things have actually taken in the recent past and then use that time in the revised plan.
2. Identify the issues that have caused the delays (what is the root cause) and develop plans to remove the causes of delay. But be realistic - if the solution was simple it probably would have been implemented by now.
3. Where you need to recover time, recognize this will need a change in performance - people will not simply work harder because you say-so....... Change in performance can be achieved by more efficient work practices, better equipment, more efficient supply-lines and/or deploying more resources but all of these need designing, planning and time spent implementing them BEFORE any improvement in performance will occur.
4. Remember Brookes Law - adding more resources to a bad project makes it worse! To be effective, before adding resources you need improvements in supervision, work practices, supplies, etc.
And all of the above cost money. Effective recovery programs burn a lot of effort and money (slowing progress in the short term) before the benefits cut in. For more on schedule compression see: https://mosaicprojects.com.au/WhitePapers/WP1059_Schedule_Compression.pdf